Grant Application Process: Final Proposal Transmittal
* If grant is due April 17
| Responsible Party/Activities: |
Timeline
|
Example*
|
PI: |
|
|
| a) |
Complete a Proposal Transmittal form and submit final proposal with the completed Program Concept Approval form to GOSC via Campus Grants Rep |
One (1) month before grant application is due if narratives have not been electronically reviewed. |
March 17 |
|
|
|
|
GOSC: |
|
|
| b) |
Reviews proposal and secure Provost and Chancellor’s signature; returns to PI signed proposal and Chancellor’s cover letter.
|
Two (2) weeks before grant application is due.
|
April 4
|
|
|
|
PI: |
|
|
| c) |
Prepares the granting agency required copies and send proposal via intercampus mail as well as electronically to the Grants One-Stop Center (GOSC). |
Three (3) days before grant application is due. |
April 14 |
|